ThyssenKrupp awarded to METEKO the structural design, connections calculations, modeling and fabrication of all steel structures for this new production building. In more details, building section were up to HEA400 with box girder of 500mm height welded with automated submerged arc welding technique. Total weight was 275tn and material grade was S275. All structures were fully hot deep galvanized.
The project was located in France. Project design started on February 2020 and fabrication of steel structures was completed by August 2020.