Thyssen Krupp asked METEKO to fabricate a complex of 12 buildings & 1310 tn relative to upgrading works in a cement plan in Outao Portugal. For the majority of buildings relative TEKLA models were sent. On these digital models only minor structure works took place (grading, checkered plates etc). Assemblies except from typical steel member include checkered plates, gratings, ladders, handrails, steps & stairs. Material grade is S235, S275 & S355. The biggest building weight was 440tn and due to tight time schedule was divided in 4 phases.

All structures were execution class 3 (EXC3) and transportation was included in METEKO’s scope.

  • Client

    THYSSENKRUPP INDUSTRIAL SOLUTIONS (France)

  • Year Completed

    2022

  • Budget

    2.850.000 €